To Purchase Sunpak Heaters, click hereReceiving EquipmentOn receipt of equipment it is suggested that a visual inspection be made for external damage to the carton. If the carton is damaged, a note should be made on the Bill of Lading when signing for the equipment. Remove the heater from the carton. If there is damage, report the damage to the carrier immediately. Important NoticeThese instructions are intended for qualified personnel, specifically trained and experienced in the installation of this type of equipment and related system components. Some states or provinces require installation and service personnel to be licensed. If your state or province is such, be sure your contractor bears the appropriate license. Persons not qualified shall not attempt to fix this equipment nor attempt repairs according to these instructions.
To Purchase Sunpak Heaters, click hereCode RequirementsInstallation must be in accordance with local codes, or in the absence of local codes, with the latest edition of the National Fuel Gas Code, ANSI Z224 and National Electrical Code ANSI/NFPA 70, and for Canada, the latest edition of CAN/CGA-B149.1 and B149.2 and Canadian Electrical Code, CSA C22.1 Part 1 and Part 2.
Gas SupplyThe gas inlet supply pressure and manifold pressure required for each heater are listed below. For gas supply line pressures in excess of psig, consult with your representative or the factory.
ClearancesEach heater must be installed such that the following "Minimum Clearance to Combustibles" are maintained. OPTIONAL MOUNTING KIT (#12006): Optional Mounting Kit is available from your heater supplier. Whether the mounting kit is used or not, minimum clearance from combustibles must be observed as follows: WARNING: The clearances shown below are also applicable to vehicles parked below heaters To Purchase Sunpak Heaters, click here
![]() To Purchase Sunpak Heaters, click hereCombustible materials include wood, compressed paper, plant fibers, plastic, Plexiglas or other materials capable of being ignited and burned. Such materials shall be considered combustible even though flame-proofed, fire retardant treated or plastered. Additional clearance may be required for glass, painted surfaces, vinyl siding or other materials which may be damaged by radiant or convection heat.
Adequate space around each heater is required even when the materials surrounding the heater are non-combustible to provide adequate combustion air and ventilation of exhaust gases. Heaters should never be located in a ceiling recess or soffit. The stated clearance to combustible materials represents a surface temperature of 90 F (32 C) above room temperature. Building materials with a low heat tolerance may be subject to degradation at lower temperatures. It is the installer's responsibility to assure that adjacent materials are not subject to degradation. In locations used for storage of combustible materials, sign shall be posted to specify the maximum permissible stacking height to maintain required clearances from the heater to combustible materials. To Purchase Sunpak Heaters, click hereFire SprinklersFire Sprinklers must be located at an appropriate distance from each heater to avoid accidental activation of the sprinkler. Ethylene glycol or propylene glycol must never be used in fire sprinkler systems where heaters are present as these substances may become flammable when heated. A fire sprinkler professional must be consulted when heaters are installed where fire sprinklers are present to insure that heaters and the fire sprinkler system are properly integrated. Specific guidelines can be found in NFPA 13 regarding design and specifications for Fire Sprinkler Systems near heaters. Heater Mounting and SupportHeaters shall be mounted in a fixed position independent of gas and electrical supply line. Hangers and brackets shall be of noncombustible material. Heaters subject to vibration shall be provided with vibration isolating hangers. Suitable materials for hanging infrared heaters are steel pipe, steel channel, or fabricated hangers of at least 16-gauge material. Hanger and brackets must be secured with adequate anchor to a secure structure using good building practices. Additional bracing to protect against seismic forces may be required in seismically active areas.
ElectricalProvide only 24 VAC with a NEC Class 2 transformer to the heaters. Each heater requires approximately 20 VA or 0.8 amps. When multiple heaters are connected to one transformer, the transformer must be sized to accommodate the entire load. A transformer must never be located inside the heater control compartment.
To Purchase Sunpak Heaters, click hereControl wire used to electrically connect one or more heaters together must have adequate capacity and insulation temperature rating for the total connected load. Use at least 18 GA wire up to 50 feet from heater to transformer or wall switch. Use a minimum of 16 GA wire for over 50 feet distance. If any of the original wire supplied with the appliance must be replaced, it must be replaced with wiring material having a temperature rating of at least 105 degrees Centigrade. Ventilation1. It is required that areas above the heater be properly vented to allow for necessary combustion air and removal of combustion gases. Gas Piping
Initial Start-Up Procedure1. Before turning on the manual gas valve to the heater verify that the control system is working properly. a. Apply 24 VAC to the heater. b. There should be an audible click and the spark initiates at the pilot. c. With the gas turned off the heater should turn "OFF" or lockout in within 10 seconds ( Synetek controls will cycle "ON" and "OFF" 3 times before lockout. d. Turn the electrical switch "OFF". 2. Turn "ON" the manual gas valve to the heater. a. Check for leaks using soapy water at all gas connections and joints. NEVER use a flame to check for leaks. b. Apply 24 VAC to heater. c. Check for pilot ignition. A smooth flame front should roll down the length of the infrared burner. Flame should stabilize on the ceramic surface. d. The ceramics portion of the infrared burner should turn RED within 5 minutes (this may be difficult to see in bright sunlight). To Purchase Sunpak Heaters, click here |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||